Tier-1 supplier. 50,000 units/year. Zero room for field failure.
8-Layer HDI Stackup
A Tier-1 automotive supplier needed an ADAS camera control unit PCB with stringent thermal and reliability requirements. The design demanded 8-layer HDI with 0.3mm pitch BGA, controlled impedance on all high-speed lanes, and IPC Class 3 throughout — at a production volume of 50,000 units/year.
Modified stackup using Panasonic Megtron 6 laminate for superior signal integrity. Laser-drilled microvias with stacked-via architecture. Custom flying-probe test program covering 100% of nets. First-pass yield stabilized at 99.2% within 3 production batches.


Startup on an FDA deadline. 10 days to functional prototypes. No margin for error.
6L Rigid-Flex · Polyimide Core
A medical device startup developing a wearable patient monitor needed a compact 6-layer rigid-flex PCB with ultra-fine 2.5/2.5mil traces, ENIG finish, and the ability to fold into a wrist-worn form factor. They were on a tight FDA submission timeline and needed functional prototypes in 10 days.
DFM review completed within 8 hours of file receipt. Used polyimide flex layers with PSA stiffeners for the folding sections. Ran parallel prototype batches to de-risk delivery. 20 functional prototypes delivered on day 10. Full production ramped to 5,000/month after FDA clearance.


287 BOM lines. 4 BGAs. 2,000 units. 8 weeks. Delivered.
Full Turnkey · 287 BOM Lines
A European smart-building company needed turnkey PCBA for their LoRaWAN + WiFi gateway. The BOM had 287 line items, including 4 BGAs, multiple RF shields, and specialty IoT sensors with 16-week lead times. They needed 2,000 units in 8 weeks with full functional testing.
Identified 14 long-lead-time components and secured allocation from 6 franchised distributors within 72 hours. Built a custom functional test station simulating LoRaWAN end-device registration and WiFi throughput. 2,000 units shipped on week 8 with 99.5% first-pass FCT yield. Re-order now running at 5,000 units/quarter.



Send us your requirements. Our engineering team will review and respond with a feasibility assessment and quotation within 24 hours.